Lesotho releases tender for Highlands Water Project Phase II


By Staff Writer | ESI Africa October 4, 2017

The Lesotho Highlands Water Project Phase II has recently launched the first of twenty infrastructure construction tenders, which will see construction commence in a few short months.

According to a project statement, the tenders will be advertised between now and mid-2019, according to the current master programme.

Lesotho Highlands Water Project – Critical Advance Infrastructure

The Polihali north-east access road is one of the critical advance infrastructure components the majority of which must be completed prior to the construction of the main Phase II works: the Polihali dam and transfer tunnel.

Tente Tente, Divisional Manager of Phase II at the LHDA, commented: “Phase II comprises a wide range of small and large contracts. It offers contractors work continuity for a number of years and the opportunity to gain valuable experience on a large infrastructure project.

“The combination of local, regional and international expertise at the consulting and contracting level will also contribute to skills transfer and capacity building within the construction and engineering sector.”

“It’s taken years of planning and preparation to get to this point, but in the first quarter of 2018, the construction vehicles will move on to site marking the start of Phase II’s six-year construction period and the eagerly anticipated employment opportunities that the project brings,” he adds.

“This is what we have been waiting for.”

Costs and Community Benefits

While the cost of the hydropower component is yet to be established, the capital investment into the water transfer component of Phase II estimated to be R23 billion [$1.6 billion] at completion in 2025, is a significantly large portion of the total projected capital investment into infrastructure in southern Africa in the next few years.

Phase II also promises a sizeable investment into the people of Lesotho, South Africa and the broader southern African region.

Skills and technology transfer are embedded in the procurement and contract documents and the attainment of specified targets will be carefully monitored and enforced.

As a general rule, preference will be given to Lesotho nationals, South African nationals, professionals from the SADC region and then internationally in that order, subject to conditions on quality, competitiveness, transparency and cost effectiveness being met.

At the height of the construction period, Phase II will provide employment for between 2,000 and 3,000 Basotho.

It will bring an influx of people into the construction area, stimulate business and increase incomes for local communities.

Expanding from Phase I

Phase II of the Lesotho Highlands Water Project builds on the successful completion of Phase I in 2003.

It delivers water to the Gauteng region of South Africa and utilises the water delivery system to generate hydro-electricity for Lesotho.

Phase II will increase the current supply rate of 780 million cubic metres per annum incrementally to more than 1 260 million cubic metres per annum.

At the same time, it will increase the quantity of electricity generated in Lesotho and is a further step in the process of securing an independent electricity source to meet Lesotho’s domestic requirements.